Strengthen the Protection of Legitimate Expectations for Investments in the Energy Transition
GESI Symbolic Image Grid
Contents

Strengthen the Protection of Legitimate Expectations for Investments in the Energy Transition

GESI Symbolic Image Grid

The Federal Network Agency intends to tie the grid fee exemption for battery storage systems to conditions that are out of touch with reality. However, it is still possible to prevent the erosion of the principle of protection of legitimate expectations.

Three years ago, on November 10, 2023, the Bundestag passed a resolution: Battery storage systems connected to the grid by the deadline of August 4, 2029, will remain exempt from grid fees. Since then, numerous project developers and investors have taken on significant financial risks in reliance on the applicable law .

But now the Federal Network Agency wants to make the protection of legitimate expectations subject to strict conditions: According to the draft specification for the General Electricity Grid Tariff System (AgNes), operators must demonstrate in the first quarter of next year that they have already made a “final investment decision ” (FID) prior to January 1, 2027.

This approach leads to significant practical problems. This is because the term “FID” is not used consistently and is therefore not an objective criterion, but rather one that depends on the specific case and the parties involved. Furthermore, developers and investors take on significant economic risks and make substantial investments (typically in the tens of millions) long before the formal FID.

Objective Criteria Instead of Unrealistic Conditions

This threatens to undermine the principle of protection of legitimate expectations, which is causing considerable uncertainty in the industry, jeopardizing private investments in the energy transition amounting to tens of billions, and calling into question the reliability of Germany as an investment destination. In our analysis, “The Final Investment Decision (FID) in the AgNes Process,” you will learn

  • Why Large-Scale Battery Projects Entail Significant Economic Risks Early On
  • at what point in the process capital is irrevocably tied up, and
  • the four criteria we proposed to the Federal Network Agency as an alternative to the FID, because they provide an objective and practical basis for assessing a project’s readiness

Download: The Final Investment Decision (FID) in the AgNes Process

Further contributions

We’ve had the pleasure of welcoming several new colleagues in recent weeks—and we need more help. We welcome applications. October 12, 2026. From procurement to project management to financial accounting: Anyone driving large-scale infrastructure projects needs expertise in a variety of areas. That’s why we’ve been actively searching for new employees over the past few months—with great success: Since July, we have welcomed ten qualified new members to the GESI...

Team GESI on a Growth Trajectory

Read more

Wind turbines along the North Sea coast often have to be throttled back. Our 740-megawatt battery farm north of Bremen will help change that. September 1, 2026. We’ve reached the next milestone: About 15 months after receiving the connection approval from grid operator TenneT, we were able to finalize the connection setup agreement (AEV) last week for our battery storage facility in Alfstedt, Lower Saxony. In addition, the planning and...

Project Update: Alfstedt (Lower Saxony)

Read more

With 2.6 GW of connected load under development, GESI currently represents one of the largest portfolios of large-scale battery storage in Germany | This is Allianz’s second direct equity investment in battery storage projects in Germany in a very short period of time April 23, 2026 | Allianz Global Investors (AllianzGI ) announced today that it has acquired a 51% stake in the battery storage platform Green Energy Storage Initiative...

PM: AllianzGI acquires 51% stake in GESI

Read more