Project Update: Alfstedt (Lower Saxony)
Screenshot taken on August 31, 2026, at 11:26:10
Contents

Project Update: Alfstedt (Lower Saxony)

Screenshot taken on August 31, 2026, at 11:26:10

Wind turbines along the North Sea coast often have to be throttled back. Our 740-megawatt battery farm north of Bremen will help change that.

September 1, 2026. We’ve reached the next milestone: About 15 months after receiving the connection approval from grid operator TenneT, we were able to finalize the connection setup agreement (AEV) last week for our battery storage facility in Alfstedt, Lower Saxony. In addition, the planning and permitting process is in full swing:

In recent weeks, in coordination with the municipality, we have initiated the urban land-use planning process as well as the environmental impact assessment procedure. The next steps include a kick-off meeting with representatives from the Trade Supervisory Office and the ordering of so-called “long-lead items”—that is, components with long lead times.

Based on the current planning status, we expect construction to begin in late summer 2027. The 740-megawatt facility in the Rothenburg (Wümme) district is therefore expected to be connected to the grid in the first half of 2029. It is urgently needed to store surplus green electricity and to fully utilize the potential of the region’s wind farms.

Recently, the problem of so-called curtailment in the north has worsened because numerous new wind farms have been connected to the grid, while there remains a lack of storage capacity and power lines to the south. Especially during the windy spring months, transmission system operators were therefore forced time and again to curtail wind farms along the coasts to ensure grid stability.

Location: Alfstedt (Lower Saxony)

Capacity: 740 megawatts

Planned commissioning: 2029

Further contributions

With 2.6 GW of connected load under development, GESI currently represents one of the largest portfolios of large-scale battery storage in Germany | This is Allianz’s second direct equity investment in battery storage projects in Germany in a very short period of time April 23, 2026 | Allianz Global Investors (AllianzGI ) announced today that it has acquired a 51% stake in the battery storage platform Green Energy Storage Initiative...

PM: AllianzGI acquires 51% stake in GESI

Read more

Following the ground investigation in March, preparations are in full swing. The Franconian municipality of Bergrheinfeld near Schweinfurt is of central importance for the German energy infrastructure. This is because the SuedLink power line, which will transport wind energy from the north to southern Germany in future, runs to this location. GESI Giga Batteries has therefore been active in Bergrheinfeld for more than two years and is driving forward one...

Project update Bergrheinfeld (Bavaria)

Read more

If you want to trigger more investment in Germany, you have to create reliable framework conditions. What is happening in energy policy Unfortunately, the opposite is currently the case. A commentary by GESI CEO Walter Raizner. Pullach, February 25. Four current examples show that energy policy is currently heading or threatening to head in the wrong direction. In the end, commercial and private electricity customers could be the ones who...

Comment: How politics fuels uncertainty

Read more