Project update Bergrheinfeld (Bavaria)
GESI-Bergrheinfeld-Web-04.2026
Contents

Project update Bergrheinfeld (Bavaria)

GESI-Bergrheinfeld-Web-04.2026

Following the ground investigation in March, preparations are in full swing.

The Franconian municipality of Bergrheinfeld near Schweinfurt is of central importance for the German energy infrastructure. This is because the SuedLink power line, which will transport wind energy from the north to southern Germany in future, runs to this location.

GESI Giga Batteries has therefore been active in Bergrheinfeld for more than two years and is driving forward one of the largest storage projects in Germany: a battery park with a capacity of 1000 megawatts is to be connected to the grid at the beginning of 2029 (see projection).

After we received the grid connection approval last year, we are now stepping up the pace: the ground investigation was carried out in March and we are currently purchasing land for environmental compensation in close coordination with the nature conservation authority.

They are also preparing the so-called application conference, which is due to take place in May. This is an expert discussion with representatives of the authorities and the public. At the same time, we are pressing ahead with the technical and electrical planning as well as the component and drainage planning. Construction work is expected to begin in the second half of next year.

Location: Bergrheinfeld

Output: 1,000 megawatts (1 gigawatt)

Planned commissioning: early 2029

Further contributions

The Federal Network Agency intends to tie the grid fee exemption for battery storage systems to conditions that are out of touch with reality. However, it is still possible to prevent the erosion of the principle of protection of legitimate expectations. Three years ago, on November 10, 2023, the Bundestag passed a resolution: Battery storage systems connected to the grid by the deadline of August 4, 2029, will remain exempt...

Strengthen the Protection of Legitimate Expectations for Investments in the Energy Transition

Read more

We’ve had the pleasure of welcoming several new colleagues in recent weeks—and we need more help. We welcome applications. October 12, 2026. From procurement to project management to financial accounting: Anyone driving large-scale infrastructure projects needs expertise in a variety of areas. That’s why we’ve been actively searching for new employees over the past few months—with great success: Since July, we have welcomed ten qualified new members to the GESI...

Team GESI on a Growth Trajectory

Read more

Wind turbines along the North Sea coast often have to be throttled back. Our 740-megawatt battery farm north of Bremen will help change that. September 1, 2026. We’ve reached the next milestone: About 15 months after receiving the connection approval from grid operator TenneT, we were able to finalize the connection setup agreement (AEV) last week for our battery storage facility in Alfstedt, Lower Saxony. In addition, the planning and...

Project Update: Alfstedt (Lower Saxony)

Read more