Memory facts series (III) | There has been repeated talk in the media recently of a “boom” in large batteries. However, there is still a huge gap between supply and demand.

“A battery tsunami is rolling in”, was the recent headline in “Der Spiegel”. A “second German energy miracle” is currently in the offing, which could make electricity cheaper than ever. Unfortunately, the subjunctive mood is more than appropriate here, for two reasons:

  • Numerous applications for the connection of large-scale battery storage systems are unlikely to be approved or will not be approved for several years – often with far lower capacities. This is because the number of suitable locations is limited. In addition, new requirements from the Federal Network Agency are calling into question the economic viability of some BESS projects.
  • In addition, approval and connection procedures often take years, even at good locations. The gap between supply and demand will therefore remain enormous for the foreseeable future. However, according to Fraunhofer ISE, Germany will need a large-scale battery storage capacity of around 100 GW by 2030. This figure is currently only 2.6 GW (see chart).

We are therefore still at the very beginning of a market ramp-up. And in the wake of the debate about expensive and highly subsidized back-up gas power plants, word is fortunately getting around that large-scale batteries are highly efficient and can therefore cover a significant proportion of storage requirements.

In addition, the next “bright breeze” will underline how urgently we need efficient storage systems to be able to absorb surplus electricity instead of having to shut down systems. Every day of delay is a day wasted – for climate protection, but also for the competitiveness of Germany as a business location.

Further contributions

Wind turbines along the North Sea coast often have to be throttled back. Our 740-megawatt battery farm north of Bremen will help change that. September 1, 2026. We’ve reached the next milestone: About 15 months after receiving the connection approval from grid operator TenneT, we were able to finalize the connection setup agreement (AEV) last week for our battery storage facility in Alfstedt, Lower Saxony. In addition, the planning and...

Project Update: Alfstedt (Lower Saxony)

Read more

With 2.6 GW of connected load under development, GESI currently represents one of the largest portfolios of large-scale battery storage in Germany | This is Allianz’s second direct equity investment in battery storage projects in Germany in a very short period of time April 23, 2026 | Allianz Global Investors (AllianzGI ) announced today that it has acquired a 51% stake in the battery storage platform Green Energy Storage Initiative...

PM: AllianzGI acquires 51% stake in GESI

Read more

Following the ground investigation in March, preparations are in full swing. The Franconian municipality of Bergrheinfeld near Schweinfurt is of central importance for the German energy infrastructure. This is because the SuedLink power line, which will transport wind energy from the north to southern Germany in future, runs to this location. GESI Giga Batteries has therefore been active in Bergrheinfeld for more than two years and is driving forward one...

Project update Bergrheinfeld (Bavaria)

Read more